Local democracy

Issue - meetings

STREET CLEANSING - SERVICE REDESIGN AND DEPLOYMENT OF RESOURCES

Meeting: 31/01/2019 - Bradford South Area Committee (Item 47)

47 STREET CLEANSING - SERVICE REDESIGN AND DEPLOYMENT OF RESOURCES pdf icon PDF 594 KB

The Bradford South Area Coordinator will submit a report (Document “Y”) which provides information on the service redesign of Street Cleansing and options for operational deployment of resources.

 

Recommended –

 

(1)       That the service redesign for gateways is adopted.

 

(2)       That Bradford South Area Committee selects its preferred delivery       model.

 

(3)       That Bradford South Area Committee will review any option        chosen after a 12 month trial period.

 

Overview and Scrutiny Committee: Environment and Waste Management

 

(Damian Fisher - 01274 437062)

Decision:

Resolved -

 

(1)       That the service redesign for gateways be adopted.

 

(2)       That Option 1b: Area Constituency pooled resources

            be selected as the preferred delivery model.

 

(3)       That the Area Committee review the option chosen after a 12 month trial period.

 

Overview and Scrutiny Committee: Environment and Waste Management

 

ACTION: Bradford South Area Coordinator

 

Damian Fisher – 01274 437062

 

Minutes:

The Bradford South Area Coordinator submitted a report (Document “Y”) which provided information on the service redesign of Street Cleansing and options for operational deployment of resources.

 

The Area Coordinator explained in detail how the Service would be redesigned around the options set out in the report.  Maps showing how the new teams would operate across Bradford South were tabled.

 

The issue of fly tipping and littering, given the large number of takeaway outlets in Bradford South were particular issues that needed addressing and enforcement was key to this.

 

In response to a question around how the proposals would work in practice, it was explained that flexibility was key in making the new system work and routes would be prioritised accordingly.

 

The Area Coordinator acknowledged that education and enforcement  were key in making the new system work.

 

Resolved -

 

(1)       That the service redesign for gateways be adopted.

 

(2)       That Option 1b: Area Constituency pooled resources

            be selected as the preferred delivery model.

 

(3)       That the Area Committee review the option chosen after a 12 month trial period.

 

Overview and Scrutiny Committee: Environment and Waste Management

 

ACTION: Bradford South Area Coordinator