IMPROVEMENT LINE REVIEW FOR HIGHWAY SCHEMES 2016.

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Resolved –

 

(1)       That Schedule A attached to Document “U” of those Highway    Improvement Lines for which the declared alignments should            continue to be protected be approved.

 

(2)       That the attached Schedule B to Document “U”of those schemes         for which the Highway Improvement Line will be protected  be           approved subject to the following modifications:

(i)    Item B1 – Tong Street replace previous HIL alignment (shown on drawing N/24315/4D and replace with drawing TDG/THS/102579/LA1 to LA3.

(ii)   Item B2 – Harrogate Road / New Line junction improvement shown on drawing TF/61/2351/5 and replace with drawing R/PTH/MH/103196/LA-19A.

 

(3)       That the attached Schedule C to Document “U” of those schemes        for which the Highway Improvement Line should be      revoked/discharged be approved.

 

(4)       That the attached Schedule D to Document “U” of those new     highway improvement lines be approved as follows:

(iii)  Item D1 – A650 Hard Ings Road, Keighley widening shown on drawings TDG/HDB/103197/PL-1A and TDG/HDB/103197/PL-2A.

(iv)Item D2 – City Connect 2, Canal Road, Bradford shown on drawings TDG/HDA/103116/IL-1A to TDG/HDA/103116/IL-8A (inclusive).

 

(5)       That a further review of Highway Improvement Lines be   undertaken following the adoption of the Local Plan with       any modifications to existing lines, or new lines to be declared, being presented to Executive.


ACTION:       Strategic Director Regeneration

 

Overview and Scrutiny Committee:  Environment and Waste Management

                                                            (Richard Gelder - 01274 437603)

 

Publication date: 21/09/2016

Date of decision: 20/09/2016

Decided at meeting: 20/09/2016 - Executive

Effective from: 28/09/2016

Accompanying Documents: